Skanska/Walsh Joint Venture LaGuardia Airport Hangar 5A Runway Drive Flushing, NY 11371
November 6, 2019
Andee Hidalgo Spearhead Construction, LLC PO Box 575 Fort Montgomery, NY 10922
Via Procore: andee@spearheadcx.com
RE: LaGuardia Airport Central Terminal Building Replacement Project (the “ Project ”); Subcontract No. 620-027 (the “ Subcontract ”) between Skanska/Walsh Joint Venture (“ SWJV ”) and Spearhead Construction LLC (“ Spearhead ); Response to Spearhead Comments to SWJV Response October 30, 2019 .
Ms. Hidalgo:
SWJV received the above referenced letter from Spearhead dated October 30, 2019. Spearhead’s assertions and contentions regarding Schedule and Verbal Direction are unsubstantiated and lack merit. SWJV provided a schedule to Spearhead. Furthermore, SWJV reaffirms the position set forth in our letter to you of October 30, 2019 and that Spearhead is obligated to meet contract durations established in Contract Exhibit D. SWJV reserves all rights and remedies under the Subcontract.
Sincerely,
Brian Mock Assistant Project Manager
cc.
Frank Corallo John Dolan
Attachments:
L.1213126J-000-620-51.1142019.1452
Page 1 of 1
SW-9312-191106-Response to Spearhead Comments to SWJV Response October 30, 2019
bm