DocuSign Envelope ID: 4BC3E417-29A4-409B-8D30-6EBEABF49DBF
EXHIBIT “B” Attachment to Subcontract/Purchase Order No. xxxxxx-xxx dated by and between [insert full legal name of Subcontractor] and Skanska/Walsh JV – Design, Furnish and Install Decorative Formed Metal and Space Heating Radiator Enclosures for Pedestrian Bridge B at LaGuardia Central Terminal Building Replacement Project, Queens, New York.
Item No.
Incl. w/ BP/Subcontract
Document
Description
Dated
Revised
MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 3 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 4 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 5 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 6 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 7 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 8 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 9 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 10 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 11 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 12 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 13 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 14 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 15 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 16 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 17 MECHANICAL BUILDING MANAGEMENT & CONTROL SYSTEM - SHEET 18
295 M80-00-00-03-00
4/13/2018
296 M80-00-00-04-00
4/13/2018
297 M80-00-00-05-00
4/13/2018 11/30/2018
298 M80-00-00-06-00
4/13/2018
299 M80-00-00-07-00
4/13/2018 11/30/2018
300 M80-00-00-08-00
4/13/2018
301 M80-00-00-09-00
4/13/2018 8/10/2018
302 M80-00-00-10-00
4/13/2018 8/10/2018
303 M80-00-00-11-00
4/13/2018
304 M80-00-00-12-00
4/13/2018 11/30/2018
305 M80-00-00-13-00
4/13/2018 8/10/2018
306 M80-00-00-14-00
4/13/2018 8/10/2018
307 M80-00-00-15-00
4/13/2018
308 M80-00-00-16-00
4/13/2018
309 M80-00-00-17-00
4/13/2018
310 M80-00-00-18-00
4/13/2018
ELECTRICAL
CONCOURSE B -ELECTRICAL ABBREVIATIONS AND SYMBOL LIST
311 E05-00-00-01-05
4/13/2018
312 E05-00-00-02-04
PEDESTRIAN BRIDGE B -ELECTRICAL SCOPE OF WORK
4/13/2018
313 E05-00-00-04-00
CONCOURSE B -CIRCUITING AND PANEL SCHEDULE LEGENDS 4/13/2018 PEDESTRIAN BRIDGE B -LEVEL 4 - ELECTRICAL COMPOSITE FLOOR PLAN PEDESTRIAN BRIDGE B -ROOF LEVEL -ELECTRICAL COMPOSITE FLOOR PLAN PEDESTRIAN BRIDGE B -ROOF LEVEL -ELECTRICAL LIGHTNING PROTECTION PLAN PEDESTRIAN BRIDGE B -LEVEL 4 - ELECTRICAL POWER PART PLAN BF PEDESTRIAN BRIDGE B -LEVEL 4 - ELECTRICAL POWER PART PLAN BG 4/13/2018 4/13/2018 4/13/2018
314 E11-AJ-4L-00-6C
315 E11-AJ-5L-00-6C
316 E12-AJ-5L-00-6C
317 E21-AJ-4L-BF-6C
4/13/2018 11/30/2018
318 E21-AJ-4L-BG-6C
4/13/2018 11/30/2018
Exhibit B
page 13 of 34
SWJV Pr. No. 1213126-000
Bid Package No./Name