Field Note
8/20/2019, 9:53 am
LGA - 620-027 — LGA CTB Replacement - PBB
When:
Text RE Elevations: Bridge sag and added concrete to deck Spearhead submitting RFI to verify new heights of ceilings/soffits due to sagging of bridge and additive concrete pour (to bring floor to AFF shown in drawings). Overall height from AFF to underside of soffit and ceiling will be less than shown on RCPs. Two issues: 1. We're installing clips, now. Need access/control points ASAP to avoid delay of work. 2. We bid to 8" CBS clips. Might have to substitute for 10" CBS clips and request change to pricing via Change Order.
Submitted By: Andee Hidalgo