LGA - 620-027 — LGA CTB Replacement - PBB

When:

Text The new shop steward started today Wednesday August 14th, he did a orientation to 11:30 , we also got two deliveries today the first one went very smoothly was studs and miscellaneous metal the second delivery was our scissor lifts there was four of them I believe they were dropped off at 11:00 and we didn't get them up until 3:45. there was an issue on how to hook up the cables to hoist it to the 4th floor

Submitted By: Gary Miuccio