BCM Additional Labor Costs Due to Covid

Message 1: Wednesday, June 24, 2020 12:39 PM

From: Carlos Quezada Arauz Sent: Wednesday, June 24, 2020 12:39 PM To: Sean ; Gary Cc: Andee ; Stavros Karanikolas ; Peter

Lambrakis (XBR) ; Michael Kourris (XBR) ; Sean Bronson (XBR) Subject: PV262-AUD Carpenter Notice to Proceed to Start Framing

Sean,

As discussed on site, based on our coordination meeting, there is a good amount of work that can be started while we wait for the GFRG panels to be delivered and installed. This notice is to inform you to please proceed as required to order any framing materials needed to frame out the areas noted, at least in the front of the stage, soffit and GFRG wall framing areas.

Thank you

Carlos Quezada Project Manager XBR Inc. 35-12 19th Avenue Suite 2E Astoria, NY 11105 T: 718-606-0072 C: 917-699-6647 F: 718-889-2229 www.xbrinc.com

The information contained in this email message is legally privileged and confidential information intended solely for the use of the intended recipient(s). If you are not the intended recipient(s), any distribution, dissemination, or reproduction of this email message is strictly prohibited. If you have received this message in error, please immediately reply to the sender and then destroy this message. The information contained in this email message is legally privileged and confidential information intended solely for the use of the intended recipient(s). If you are not the intended recipient(s), any distribution, dissemination, or reproduction of this email message is strictly prohibited. If you have received this message in error, please immediately reply to the sender and then destroy this message.

Back to message list

Made with FlippingBook. PDF to flipbook with ease