BCM Additional Labor Costs Due to Covid
Spearhead Construction, LLC
Brooklyn Children'sMuseum
3/3/22
Spearhead Progression of Work
Period Spearhead Work Timeline 5-Dec-19 Spearhead Preliminary Start (Delayed) - Field Survey 3-Feb-20 Spearhead Actual Preliminary Start - Field Survey 15-Apr-20 Covid-19 Delay. NYC Buildings Covid-19 Shutdown 29-Apr-20 Previously Scheduled Start. Delayed. 9-Jun-20 Recommence work 24-Jun-20 Spearhead Notice to Proceed 1-Jul-20 New Wage Rates Jul-20 Spearhead Crews on site Aug 2020 through Dec 2020 Delay. Waiting on Predecessor trades. GFRG mock up (2 days). 25 Jan 2021 through Jun 2021 Spearhead Crews on Site 1-Jul-21 New Wage Rates Jul 2021 through Nov 2021 Minimal Crews on Site Dec 2021 to present Work complete. Preliminary Punchlist Complete. Demobed.