BCM Additional Labor Costs Due to Covid
Cost / Rate
Qty / Hrs
Description
Workers
Ext
Wage Rate Period: 1 July 2020 to 30 Jun 2021
10.12 Hrs
Finisher
$94.78
1.00
$959.17
Wage Rate Period: 1 July 2021 to 30 Jun 2022
Breakout
Labor : $81,902.61 Overhead Percent @ 23.2%: $19,001.41 _____________ Total: $100,904.02
Reservation of Rights This COR does not include any amount for impacts such as interference, disruptions, rescheduling, changes in the sequence of work, delays and/or associated acceleration. Spearhead Construction, LLC expressly reserves the right to submit our request for any of these items.
Signed By:
Dated: 2/28/2022
__________________________